General
It is anticipated that full refurbishment of lifts will be completed at Aberdeen, Aden, Aldenham and Australia Towers in Lakeside and also Devonshire and Eglinton Towers
The completion of our pioneering first ground source heat project (Core364) will be completed in the seven tower blocks in North Sunderland
A pre paint repairs and external decoration programme will take place in Ayton, Usworth, Marley Pots and Fulwell. The internal communal decoration of low rise blocks will also continue.
Continuation of porch renewals in Town End Farm Sunderland see a further 22 completions.
Heating
Area |
No of Properties |
Central |
1 |
North |
121 |
South |
376 |
Houghton & Hetton |
332 |
Washington |
9 |
Roof Renewal
Area |
No of Properties |
Central |
153 |
North |
83 |
South |
354 |
Houghton & Hetton |
81 |
Washington |
47 |
Window Replacement
Area |
No of Properties |
Central |
673 |
North |
383 |
South |
485 |
Houghton & Hetton |
507 |
Washington |
368 |
(These replacements numbers include 301 properties moved from 19/20 to 2/21).