General
In 2019-20 we carried out refurbishments to both lifts in Altrincham and Amble Towers in Lakeside. We also completed 46 Porch renewals in Town End Farm
Pre paint repairs and external decoration was completed in Town End Farm, Ryhope, Witherwack and Ford Estate. Internal communal decoration was completed in Astral, Solar and Planet House, City Centre, Hedworth, South Durham and D’Arcy Court Hendon, Benedict and City Green, City Centre and Amalphi Tower in Lakeside. A further 60 low rise block across the City also received communal decoration.
Roof Renewals
Area |
No of Properties |
Central |
280 |
North |
2 + 5 multi storey blocks |
South |
83 |
Houghton & Hetton |
183 |
Washington |
182 |
In addition planned brickwork repairs were completed on 98 properties.
Boiler Replacement
Area |
No of Properties |
Central |
4 |
North |
11 |
South |
1020 |
Houghton & Hetton |
62 |
Washington |
378 |
An additional 383 boiler replacements were competed responsively throughout the year.
Window Replacements
Area |
No of Properties |
Central |
187 |
North |
307 |
South |
289 |
Houghton & Hetton |
234 |
Washington |
8 |
Internal Replacements
Area |
No of Properties |
Central |
26 |
North |
98 |
South |
17 |
Houghton & Hetton |
7 |
Washington |
14 |